<?xml version="1.0" encoding="UTF-8"?><!DOCTYPE wml PUBLIC "-//WAPFORUM//DTD WML 1.1//EN" "http://www.wapforum.org/DTD/wml_1.1.xml">
<wml>
<head> 
<meta http-equiv="Expires" content="0"/> 
<meta http-equiv="Cache-Control" content="no-cache"/> 
<meta http-equiv="Pragma" content="no-cache"/> 
</head>
<card title="国道212线漳县分水岭水毁路段恢复通车_CmsTop">
	<p><a href="https://wap.xinxilanzhou.com/">首页</a> &gt; <a href="https://wap.xinxilanzhou.com/?action=category&amp;catid=1">资讯</a> &gt; <a href="https://wap.xinxilanzhou.com/?action=category&amp;catid=7">甘肃</a> &gt; </p>
	<p align="center"><big>国道212线漳县分水岭水毁路段恢复通车</big></p>
	<p align="right">2021-01-04 10:10</p>
	<p>
                国道212线漳县分水岭&nbsp;水毁路段恢复通车<br />

<p align="center"><img src="https://upload.xinxilanzhou.com/2021/0104/thumb_100_100_1609726250322.jpg" /><br /><a href="https://wap.xinxilanzhou.com/?action=image&amp;path=2021/0104/1609726250322.jpg">查看原图</a></p><br />

抢修施工（定西公路局供图）<br />



　信息兰州网1月4日讯 据兰州晚报报道&nbsp;&nbsp;2020年12月30日上午11时30分，因水毁中断138天的国道212线漳县分水岭段恢复通车。<br />

受汛期持续强降雨影响，2020年8月13日6时，国道212线分水岭K170+050-180段发生山体滑塌，垮塌土石5000余立方米，造成交通中断。险情发生后，定西公路局迅速组织人员开展应急抢修。抢修工程采用&ldquo;路基回填+拱形骨架+锚索抗滑桩+防排水&rdquo;综合治理措施。据统计，分水岭滑坡抢修工程共开挖土方2.1万立方米，浇筑直径2米抗滑桩1000米和直径1.5米抗滑桩384米，预制安装挡土板496立方米、仰斜式挡土墙779立方米。为确保通车后车辆通行安全，连日来，漳县公路段组织人员和机械车辆，在零下20多度的严寒中，对分水岭路段冰雪进行了及时清理。<br />

受冬季天气影响，该路段的路面及部分防护、排水工程尚未完善，计划于今年4月初开工。<br />

兰州日报社全媒体记者&nbsp;谭安丽<br />

		
                



		</p>
		<p><a href="https://wap.xinxilanzhou.com/?action=comment&amp;contentid=45721">共有评论0条</a></p>
<p><anchor title="返回"><prev/>&lt;返回</anchor><br /><br /><a href="https://wap.xinxilanzhou.com/" title="返回首页">&lt;返回首页</a></p>
<p align="center">Copyright CmsTop.com<br />2026年05月07日 21:53:57</p></card>
</wml>