<card title="兰州汽车新东站明年6月投运 站址位于东岗东路原兰州皮革厂生产区_CmsTop">
	<p><a href="https://wap.xinxilanzhou.com/">首页</a> &gt; <a href="https://wap.xinxilanzhou.com/?action=category&amp;catid=1">资讯</a> &gt; <a href="https://wap.xinxilanzhou.com/?action=category&amp;catid=7">甘肃</a> &gt; </p>
	<p align="center"><big>兰州汽车新东站明年6月投运 站址位于东岗东路原兰州皮革厂生产区</big></p>
	<p align="right">2020-12-11 09:41</p>
	<p>
                兰州汽车新东站明年6月投运<br />

站址位于东岗东路原兰州皮革厂生产区<br />


<p align="center"><img src="https://upload.xinxilanzhou.com/2020/1211/thumb_100_100_1607650865914.jpg" /><br /><a href="https://wap.xinxilanzhou.com/?action=image&amp;path=2020/1211/1607650865914.jpg">查看原图</a></p><br /> 


兰州汽车新东站主体已完工。掌上兰州&middot;兰州晨报记者&nbsp;王思璇&nbsp;摄<br />

信息兰州网12月11日讯（掌上兰州&middot;兰州晨报记者王思璇）12月10日，记者从兰州运输集团获悉，兰州汽车新东站项目主体工程已完工，安装工程已完成80％，车站外立面石材和玻璃幕墙装饰工程基本完成，计划2021年6月完成全部配套工程并投入运行。<br />

兰州汽车新东站项目于2016年3月全面开工建设，项目总投资3亿元，站址位于东岗东路原兰州皮革厂生产区，项目用地面积为85亩，建设用地约55亩，总建筑面积为123603平方米。其中，车站建筑面积为39302平方米，目前，新车站主体均已完工，候客大厅、售票大厅正在进行室内装修。在候客大厅里，新增加了母婴室、治安室、残疾人通道，而且母婴室内配有专门的洗手间和检票口。车站还增加了落客洗手间，乘客在下车的地方即可就近如厕，洗手间的面积约为100平方米。目前室外正在进行地下车库东西侧坡道施工，地下车库将为接送乘客、临时停放和员工提供300个车位。<br />

据兰运集团副总经理陈常庆介绍，兰州汽车新东站按照国家一级汽车客站标准设计，候车大厅可容纳万人以上，日发送量2万人次，吞吐量达4万人次，日发送班次400-600班。同时，主体工程的门头装饰工程计划明年开春天气转暖正式施工，该工程设计为一幅山水画，面积为500平方米左右。<br />

		
                



		</p>
		<p><a href="https://wap.xinxilanzhou.com/?action=comment&amp;contentid=42064">共有评论0条</a></p>
<p><anchor title="返回"><prev/>&lt;返回</anchor><br /><br /><a href="https://wap.xinxilanzhou.com/" title="返回首页">&lt;返回首页</a></p>
<p align="center">Copyright CmsTop.com<br />2026年05月01日 17:52:34</p></card>
</wml>