	<p align="center"><big>甘肃省内首台330千伏主变压器顺利启动</big></p>
	<p align="right">2022-09-30 21:42</p>
	<p>
                <p align="center"><img src="https://upload.xinxilanzhou.com/2022/0930/thumb_100_100_1664545324152.jpg" /><br /><a href="https://wap.xinxilanzhou.com/?action=image&amp;path=2022/0930/1664545324152.jpg">查看原图</a></p><br />

9月26日，国网兰州供电公司变电检修人员苟方、汪振亮正在进行变压器高压套管等附件的安装工作。（王晖/摄）<br />

每日甘肃网讯（新甘肃&middot;每日甘肃网记者&nbsp;王梓懿&nbsp;通讯员&nbsp;王生鹏&nbsp;王鹏）9月29日凌晨2时，随着330千伏和平变电站2号主变压器第一次充电成功，标志着甘肃省内首台主变压器安装工作顺利启动。<br />

据了解，和平变电站作为兰州东部电网枢纽站，承担着兰州东部城区及榆中地区供电任务，随着该区域用电负荷持续增长，原2号主变压器因抗短路能力不足，无法满足电网安全运行需求。围绕服务&ldquo;双碳&rdquo;目标及提升变压器能效，国网兰州供电公司统筹设备使用寿命积极稳妥推进在运变压器改造。和平变2号主变压器更换，将有效提高主变压器能效及解决主变压器抗短路能力不足问题，消除设备存在的隐患，完成后将有力保障电力可靠供应。作为首次自主实施的330千伏主变压器安装项目，国网兰州供电公司仅用16天完成新变压器的就位安装、电气试验、保护调试工作，新主变压器一次启动成功。<br />

下一步，国网兰州供电公司将继续聚焦电网设备的可靠运行，推进核心业务的全覆盖自主实施，保证兰州电网的安全稳定。<br />

		
                



		</p>
		<p><a href="https://wap.xinxilanzhou.com/?action=comment&amp;contentid=179315">共有评论0条</a></p>