<card title="S10凤合高速马坞西寨花台山隧道双洞顺利贯通_CmsTop">
	<p><a href="https://wap.xinxilanzhou.com/">首页</a> &gt; <a href="https://wap.xinxilanzhou.com/?action=category&amp;catid=1">资讯</a> &gt; <a href="https://wap.xinxilanzhou.com/?action=category&amp;catid=7">甘肃</a> &gt; </p>
	<p align="center"><big>S10凤合高速马坞西寨花台山隧道双洞顺利贯通</big></p>
	<p align="right">2022-09-28 09:01</p>
	<p>
                S10凤合高速马坞西寨花台山隧道双洞顺利贯通<br />

<p align="center"><img src="https://upload.xinxilanzhou.com/2022/0928/thumb_100_100_1664326866893.jpg" /><br /><a href="https://wap.xinxilanzhou.com/?action=image&amp;path=2022/0928/1664326866893.jpg">查看原图</a></p><br />

花台山隧道效果图。<br />

每日甘肃网9月28日讯（奔流新闻&middot;兰州晨报通讯员 桂莲蓬 记者 欧阳海杰）由中冶路桥建设有限公司承建的S10凤合高速马坞西寨一期工程花台山隧道，9月19日实现全线率先双洞贯通，目前该项目道路工程、桥梁工程、隧道工程等施工建设任务同步推进，预计2023年年中实现全线贯通。<br />

花台山隧道为分离式隧道，隧道全长1729米，采用双向4车道设计，设计时速80千米，于2021年6月3日动工建设。据施工方介绍，因地质、气候等各类因素叠加，该隧道施工风险高、难度大，洞口地形存在偏压等问题，为了突破这一个个难点，施工中采用国内先进的湿喷机械手、数字锚杆台车、液压模板栈桥、防水板挂布台车等施工设备，提高了隧道的精细化施工水平，并利用锁脚锚管导向架、仰拱钢筋导向架等微改微创新技术，提高了隧道施工质量精度控制。同时，运用多功能空气监测器、隧道台车视频监视器、洞内人员定位等信息化管理手段，提升隧道施工安全管理水平。<br />

&ldquo;建设团队在&lsquo;重、难、急、苦&rsquo;的施工环境下，以&lsquo;党建+赋能&rsquo;，开展隧道科研创新研究，并取得实用新型专利2项，为隧道的顺利贯通提供了技术、质量、安全等全方位的有力保障。&rdquo;施工方说，中冶路桥务实、担当、协作、进取的企业文化，在隧道建设中得到了升华。<br />

据悉，一期工程建成后将进一步完善区域路网结构，将G75兰海高速渭源至武都段与S10凤合高速卓尼至合作段连接，贯通岷县至合作方向，带动项目沿线群众致富，促进区域经济社会协调发展。<br />

		
                



		</p>
		<p><a href="https://wap.xinxilanzhou.com/?action=comment&amp;contentid=178859">共有评论0条</a></p>