	<p align="center"><big>兰州首座风电场正式投运</big></p>
	<p align="right">2021-12-31 10:01</p>
	<p>
                兰州首座风电场正式投运<br />

<p align="center"><img src="https://upload.xinxilanzhou.com/2021/1231/thumb_100_100_1640916066868.jpg" /><br /><a href="https://wap.xinxilanzhou.com/?action=image&amp;path=2021/1231/1640916066868.jpg">查看原图</a></p><br />

首座风电厂正式投运&nbsp;李&nbsp;昕&nbsp;摄<br />



信息兰州网12月31日讯 据兰州日报报道 12月29日，华能中川风电场全容量启动并网发电，标志着兰州首座风电厂正式投运，有效改善了兰州电网的电源结构。<br />

据了解，华能永登坪城45兆瓦风电项目位于永登县坪城乡境内，项目装机容量45兆瓦，安装3.6兆瓦风电机组12台、1.8兆瓦风电机组1台，设计年有效利用小时数约2170小时，年均发电量约9765万千瓦时，每年节约标准煤约2.83万吨。<br />

该项目自6月份开工建设以来，国网兰州供电公司各部门密切协作，积极与业主单位沟通，服务新能源发电企业，向新能源企业介绍并网工作机制及调度运行管理的相关要求，有序推进项目建设。同时，该公司电力调度中心按计划组织完成330千伏中川变110千伏中正双回线继电保护装置改造、定值及启动方案编制下发、正路变110千伏备自投试验等工作，为确保华能中川风电场按期投运奠定了基础。<br />

据悉，华能中川风电场按期投运，不仅标志着兰州电网有了风电机组，同时意味着兰州新区电网电源结构的进一步丰富，主变下网功率的进一步平衡，一定程度上缓解了主网断面重载的局面。下一步，国网兰州供电公司将齐心协力，持续做好新能源并网服务工作，强化新能源并网运行管理等工作，为实现&ldquo;碳达峰、碳中和&rdquo;目标贡献力量。<br />

兰州日报社全媒体记者&nbsp;李&nbsp;昕<br />

		
                



		</p>
		<p><a href="https://wap.xinxilanzhou.com/?action=comment&amp;contentid=158600">共有评论0条</a></p>
<p><anchor title="返回"><prev/>&lt;返回</anchor><br /><br /><a href="https://wap.xinxilanzhou.com/" title="返回首页">&lt;返回首页</a></p>
<p align="center">Copyright CmsTop.com<br />2026年05月10日 07:48:36</p></card>
</wml>