<?xml version="1.0" encoding="UTF-8"?><!DOCTYPE wml PUBLIC "-//WAPFORUM//DTD WML 1.1//EN" "http://www.wapforum.org/DTD/wml_1.1.xml">
<wml>
<head> 
<meta http-equiv="Expires" content="0"/> 
<meta http-equiv="Cache-Control" content="no-cache"/> 
<meta http-equiv="Pragma" content="no-cache"/> 
</head>
<card title="兰州白塔山隧道建成啥样了？记者带你实地探访_CmsTop">
	<p><a href="https://wap.xinxilanzhou.com/">首页</a> &gt; <a href="https://wap.xinxilanzhou.com/?action=category&amp;catid=1">资讯</a> &gt; <a href="https://wap.xinxilanzhou.com/?action=category&amp;catid=8">兰州</a> &gt; </p>
	<p align="center"><big>兰州白塔山隧道建成啥样了？记者带你实地探访</big></p>
	<p align="right">2021-12-05 10:49</p>
	<p>
                兰州白塔山隧道建成啥样了？&nbsp;记者带你实地探访<br />

<p align="center"><img src="https://upload.xinxilanzhou.com/2021/1205/thumb_100_100_1638672547565.jpg" /><br /><a href="https://wap.xinxilanzhou.com/?action=image&amp;path=2021/1205/1638672547565.jpg">查看原图</a></p><br />



　信息兰州网12月4日讯（奔流新闻&middot;兰州晨报记者熊园）自开建一年多来，黄河流域兰州白塔山段综合提升改造项目进展情况备受社会关注。12月1日，记者在施工现场看到，该项目一期工程现场作业区一片繁忙，多台装载土方的车辆穿梭其间，机械正在积极作业，工人们抓紧施工。隧道内，挖掘工作也在有序进行中。<br />

施工现场管理人员刘子昌告诉记者，现阶段项目施工任务主要以岩土工程、桥梁工程及隧洞工程为主，截至12月1日，隧道工程东洞口北线已进入正常开挖、支护、衬砌工序循环阶段，掘进突破200米。东洞口岩土工程24根抗滑桩，已全部完成桩身开挖及整体混凝土浇筑，D型、E型桩正处于挡土板施工阶段；西洞口岩土工程18根抗滑桩，已完成6根桩身开挖及整体混凝土浇筑，剩余12根正处于桩身开挖施工阶段。<br />

据悉，2020年10月15日，黄河流域兰州白塔山段综合提升改造项目开工。一期工程为黄河流域兰州白塔山段河堤保护治理工程，建设内容为隧道交通工程；二期工程为黄河流域兰州白塔山段黄河文化保护工程，建设内容为桥北广场以及烧盐沟仿古建筑群。<br />

图/奔流新闻&middot;兰州晨报记者&nbsp;裴强<br />

		
                



		</p>
		<p><a href="https://wap.xinxilanzhou.com/?action=comment&amp;contentid=151466">共有评论0条</a></p>
<p><anchor title="返回"><prev/>&lt;返回</anchor><br /><br /><a href="https://wap.xinxilanzhou.com/" title="返回首页">&lt;返回首页</a></p>
<p align="center">Copyright CmsTop.com<br />2026年05月09日 22:52:46</p></card>
</wml>